Aging Hardware Nearing End of Support
The on-premises Oracle servers were approaching end-of-life, and the network faced a six-figure capital refresh to keep running the same architecture for another hardware cycle.
A regional healthcare network needed to exit an aging on-premises Oracle data center footprint without disrupting a database that clinical and scheduling systems depend on around the clock. OptiSol used GoldenGate-based replication to move the database to AWS RDS for Oracle with a cutover window measured in minutes, not hours.
The database sat behind patient scheduling, clinical documentation, and billing systems that could not tolerate an extended outage, which made every prior modernization attempt stall at the planning stage.
The on-premises Oracle servers were approaching end-of-life, and the network faced a six-figure capital refresh to keep running the same architecture for another hardware cycle.
Clinical documentation and scheduling systems that depend on the database run continuously, so any migration approach requiring a traditional overnight or weekend outage window was a non-starter.
Enrollment periods and seasonal patient volume drove workload spikes the fixed on-premises hardware was increasingly unable to absorb without manual intervention.
Rather than a big-bang migration, OptiSol kept the AWS RDS for Oracle target in continuous sync with the on-premises source for weeks before cutover — so the actual switch was a brief, well-rehearsed final step.
OptiSol inventoried the Oracle estate — schemas, jobs, linked objects, and dependencies — and captured AWR baselines to establish exactly what "normal" performance looked like before any migration work began.
Compute and storage for AWS RDS for Oracle were sized directly against the AWR-observed workload, and a Multi-AZ configuration was designed to give the network built-in high availability it didn't have on-premises.
An initial RMAN-based load populated the RDS target, after which Oracle GoldenGate captured and applied ongoing changes in near real time — keeping the cloud target continuously current with the live on-premises database for the following weeks.
The cutover sequence — freeze writes, let GoldenGate apply the final lag, redirect application connections — was rehearsed twice against a staging copy before the production cutover window, with a tested fallback to reverse the replication direction if needed.
Performance was tracked against the on-premises AWR baseline for 30 days post-cutover, with CloudWatch alarms tied to the same thresholds the network used to judge on-premises health.
"The cutover was almost anticlimactic — which is exactly what we wanted for a database this critical. All the real work happened in the weeks of replication before it." — OptiSol Oracle Engineering Lead
Let's Talk
Tell us what you are running today and where you need expert support.
"*" indicates required fields
Global Presence
Five global locations. One connected engineering team.
North America
Chennai · Coimbatore
Client services
Regional operations
Client services